India's first high-speed rail service is scheduled to commence operations in the last quarter of 2027, according to Railway Minister Ashwini Vaishnaw.
The first operational stretch of the network will connect Surat to Vapi. Vaishnaw stated that the full corridor connecting to Mumbai will subsequently open in phases.
Status of construction work
Significant civil construction milestones have been achieved on the project. By September, teams had finished 371 km of viaduct construction alongside 456 km of pier work.
Infrastructure installations are also progressing along the corridor. A total of six lakh noise barriers have been installed along a 299 km stretch, while 9,300 overhead equipment (OHE) masts have been set up across a 206 km viaduct.
The Mumbai-Ahmedabad High-Speed Rail corridor marks India's first under-construction high-speed rail line. The project is being executed by the National High Speed Rail Corporation Limited (NHSRCL) and utilizes Japan's Shinkansen technology.